Gas piping systems in all buildings, except for one- and two-family homes, and other buildings classified in Occupancy Group R-3, must be inspected by a Licensed Master Plumber (LMP), or a qualified individual working for an LMP. Gas piping systems must be inspected at least once every four years according to the schedule below.

Date Range for InspectionBuildings in Community Districts


January 1, 2020 - December 31, 2020 *1, 3, 10 in all boroughs

January 1, 2021 - December 31, 2021 *2, 5, 7, 13, 18 in all boroughs

January 1, 2022 - December 31, 2022 *4, 6, 8, 9, 16 in all boroughs

January 1, 2023 - December 31, 2023 *11, 12, 14, 15, 17 in all boroughs


*and no later than December 31 within every fourth calendar year thereafter

NOTE: The deadline for buildings in Community Districts 2, 5, 7, 13, and 18 in all boroughs has been extended! These buildings are not required to submit Gas Piping System Periodic Inspection Certifications until June 30, 2022. Please see additional information regarding this extension.

To determine which Community District your building is in, please visit the NYC Department of City Planning’s website and search the address of your building. Once you determine your Community District and applicable inspection deadline from the schedule above, use the following step-by-step guide to comply with Local Law 152 of 2016 Periodic Inspections of Gas Piping Systems.


Local Law 152 of 2016 Step-by-Step Compliance Guide

STEP 1: Determine if your building is required to comply with Local Law 152 of 2016.


LL152 of 2016 applies to all buildings except one- and two-family homes and other buildings classified in occupancy group R-3. If your building is classified under the following classification codes, you do not need to comply with LL152 of 2016: A0, A1, A2, A3, A4, A5, A6, A7, A8, A9, B1, B2, B3, B9, M3, M4, or N2.


The occupancy group classification for your building is listed on the Certificate of Occupancy (CO) for your building. To find the CO for your building, follow the instructions on DOB’s website. If no CO for your building is available, look for the NYC Department of Finance’s Building Classification on the building’s Property Profile in the Buildings Information System (BIS).


STEP 2: If LL152 of 2016 applies to your building but the building does not contain gas piping


If your building does not contain gas piping, a Gas Piping System Periodic Inspection Certification, signed and sealed by a Registered Design Professional (a New York State licensed professional engineer or registered architect) or a Licensed Master Plumber, stating that such building contains no gas piping must be submitted to DOB. No further action is necessary.


STEP 3: If LL152 of 2016 applies to your building, the building contains gas piping, and the building is currently supplied with gas


Hire a Licensed Master Plumber (LMP) to Inspect the Gas Piping System in Your Building. LMPs are licensed by DOB to perform plumbing work in New York City. DOB encourages anyone hiring an LMP to check both their current license status and disciplinary and voluntary surrender records.

Before hiring an LMP:

  • Use the License Search tool to make sure the LMP's license is active. The tool allows you to search a licensee by name, business name, or license number.

  • Review the disciplinary actions taken against a licensee by DOB or voluntary surrender records by using the Know Your Construction Professional tool.

If are unable to have your building inspected by the deadline of your reporting year, you can request a one-time 180-day extension of the due date using the online portal. You must have your building inspected before the extension period expires.


STEP 4: LMP must submit a Gas Piping System Periodic Inspection Report to the building owner within 30 days of inspection


Within 30 days of the inspection, the LMP you hired must provide you with a Gas Piping System Periodic Inspection Report showing the results of the inspection.


If an inspection reveals any unsafe or hazardous condition(s), the LMP must immediately notify you, the utility providing gas service to your building, and DOB. You must take immediate action to correct the unsafe or hazardous condition(s) in compliance with the NYC Construction Codes, including obtaining any required work permits.


STEP 5: Submit Gas Piping System Periodic Inspection Certification to DOB within 60 days of inspection


Within 60 days of the inspection, you must submit a Gas Piping System Periodic Inspection Certification signed and sealed by the Licensed Master Plumber who conducted or supervised the inspection using DOB's using online portal.


  • If the Gas Piping System Periodic Inspection Certification submitted to DOB indicates that conditions requiring correction were identified during the gas piping system inspection, you must submit to DOB, within 120 days of the inspection, a Gas Piping System Periodic Inspection Certification signed and sealed by the Licensed Master Plumber who conducted the inspection, stating that the conditions have been corrected.

  • If the Gas Piping System Inspection Certification submitted to DOB indicated that additional time was needed to correct the condition(s) identified during the gas piping system inspection, you must submit to DOB, within 180 days of the inspection, a Gas Piping System Periodic Inspection Certification signed and sealed by the Licensed Master Plumber who conducted the inspection, stating that the conditions have been corrected.

  • Correction of conditions identified during a gas piping system inspection must be performed in compliance with the New York City Construction Codes, including obtaining any required work permits.

Failure to file a Gas Piping System Periodic Inspection Certification by the applicable due date may result in a civil penalty of $5,000.


STEP 6: If LL152 of 2016 applies to your building and your building contains gas piping, but the building is not currently supplied with gas and has no appliances connected to the gas piping


You must submit to DOB, through the online portal, the following two documents:

  1. a signed statement from the utility company containing: containing the following: - the last date gas was supplied to the building; and - the date on which gas service was no longer provided to the building; and

  2. a signed statement from the owner of the building containing the following: - a certification that the building no longer receives gas service; and - a certification that the building no longer contains appliances connected to gas piping.

To request a statement from your utility company, contact:

  • ConEdison: (800) 643-1289, select option #2

  • National Grid: nycdisconnects&reconnects@nationalgrid.com

Before resuming gas service to the building, the owner must hire a Licensed Master Plumber to obtain a DOB permit and conduct all gas-related inspections; submit a Gas Authorization Request in DOB NOW: Inspections; and submit the Gas Piping System Periodic Inspection Certification through the online portal.

If you have any additional questions about this requirement, please contact LL152of16@buildings.nyc.gov.


Local Law 152 of 2016 Updates

  • Follow-up #6 - Local Law 152 of 2016: Requests for Due Date Extensions to Complete Gas Piping Inspections (March 2022)

  • Follow-Up #5 - Local Law 152 of 2016: Licensed Master Plumbers Allowed to Certify a Building Does Not Contain Gas Piping; Procedures for Certifying a Building Is Not Supplied with Gas (December 2021)

  • Follow-up #4 – Local Law 152 of 2016: Gas Piping Inspections Deadline for Community Districts 2, 5, 7, 13, and 18 in all Boroughs Extended (December 2021)

  • Follow-Up #3: Local Law 152 of 2016: Gas Piping Inspections Deadline for Community Districts 1, 3 and 10 in all Boroughs Extended (December 2020)

  • Follow-Up #2: Local Law 152 of 2016: Periodic Inspection of Gas Piping Systems Required (October 2020)

  • Follow-Up #1: Local Law 152 of 2016: Periodic Inspection of Gas Piping Systems Required (January 2020)

Additional Resources

  • Get information on Local Law 152 of 2016

  • Get information on Local Law 152 of 2016 rules (1 RCNY §103-10)

  • See Local Law 152 of 2016 FAQ

5 views0 comments

Comments


Get A Proposal

GET A PROPOSAL

Upload Project Files

For any inquiries, questions, or recommendations, please call 646.481.1861 or send us an email and we'll get the ball rolling from there.

To apply for a job with BUILT Engineers, please send a cover letter together with your resume.

BUILT Engineers

447 Broadway, FL 2 #A200

New York, NY 10013

 

info@builtengineers.com

646.481.1861

© 2021 by BUILT ENGINEERS

Talk to a Licensed Professional Engineer today: 646.481.1861

  • LinkedIn
  • Instagram
bottom of page